I'm going to visit my local bank and check into getting financing for 1 of 2 big projects I have planned. I don't think I have the room to do both big projects and will instead try to shoot for 1 and do the other sometime next year. So, I was wondering if anyone had an opinion on which project I should pursue.
Project 1: Adding a self serve dog wash. This would require a new building and buying a new water heater, equipment, and all the necessary things to get going from scratch. I am located a block or two away from Petco and Petsmart on a busy street with no self serve dog wash competition. I would probably initially start with 3 dog wash stations @ $5 for 10 min. I'm thinking I can get this project done for $50,000.
Project 2: Bay Upgrades: Installing new plastic sheeting around all my 8 self serve bays. Upgrading my current quarter only acceptance meters to coin, bill, and credit card meters. Installing doors on all 8 bays, installing new signage and new lighting. I'm thinking this project will also cost around $50K.
As far as needs go, I really need to do a bay upgrade. The visual appeal of my bays needs improved and my quarter only acceptance is lagging behind other washes. But, business remains strong and I think I can get by another year before having to do this.
The dog wash would be a 2nd source of income from the site and I'm thinking the extra 15-20K each year would make it much easier to get financing for the bay upgrade next year. While a bay upgrade this year will likely not bring in 15-20K extra like the dog wash would, making the dog wash something I would have to wait 2 years for if I chose to upgrade the bays first.
Any opinions on this? Would 50K cover a dog wash with 3 stalls and a new building? Any help would be much appreciated.
Project 1: Adding a self serve dog wash. This would require a new building and buying a new water heater, equipment, and all the necessary things to get going from scratch. I am located a block or two away from Petco and Petsmart on a busy street with no self serve dog wash competition. I would probably initially start with 3 dog wash stations @ $5 for 10 min. I'm thinking I can get this project done for $50,000.
Project 2: Bay Upgrades: Installing new plastic sheeting around all my 8 self serve bays. Upgrading my current quarter only acceptance meters to coin, bill, and credit card meters. Installing doors on all 8 bays, installing new signage and new lighting. I'm thinking this project will also cost around $50K.
As far as needs go, I really need to do a bay upgrade. The visual appeal of my bays needs improved and my quarter only acceptance is lagging behind other washes. But, business remains strong and I think I can get by another year before having to do this.
The dog wash would be a 2nd source of income from the site and I'm thinking the extra 15-20K each year would make it much easier to get financing for the bay upgrade next year. While a bay upgrade this year will likely not bring in 15-20K extra like the dog wash would, making the dog wash something I would have to wait 2 years for if I chose to upgrade the bays first.
Any opinions on this? Would 50K cover a dog wash with 3 stalls and a new building? Any help would be much appreciated.