This weekend, I will be working on installing my auto cashier. I still have to run conduit and pretty much do everything involved in installing one. Any tips or tricks I could use to ensure a smooth install? I would much rather learn from all of your guys' mistakes. :D

Thanks!
 

chaz

Active member
Joined
Mar 22, 2008
Messages
920
Reaction score
111
Points
43
Location
Cincinnati, Ohio
run an extra conduit (or two) for future use. possible additional lighinting or cat5
 

Randy

Well-known member
Joined
Sep 5, 2007
Messages
5,858
Reaction score
2,208
Points
113
How are you planning on mounting the ACW? Brick mount or Pedestal mount? You’re going to want to pour a concrete pad for either way of installing the ACW. I always run 4 ¾” conduits, thinking about future upgrades etc. We brick mount everything here.
 

raisetheprice

Member
Joined
Sep 5, 2007
Messages
252
Reaction score
0
Points
16
I'm assuming you will have doors at some point and this may not matter, but if you have the room put it far enough back where it (and your customers) doesn't get a bath during high pressure. If you're converting a SS bay, it's probably a little shorter and spray will come out. Our bays were build for an auto and the ACWs are too close to the bays and the brick is impossible to keep clean.
 
Last edited:

pitzerwm

Active member
Joined
Aug 28, 2007
Messages
3,693
Reaction score
10
Points
36
Location
Tri-Cities, WA
I also ran a 4" pipe, and later needed to pump cool air from the equipment room during the summer because of the heat inside it.
 

Buzzie8

Member
Joined
Dec 12, 2007
Messages
942
Reaction score
2
Points
16
Location
Pittsburgh, PA
Bollards, bollards, and more bollards. I recently replaced my entry unit and added bollards to both sides. It's only been four months and the bollards have been hit about three times. Make sure they are thick and sturdy. I would use them on brick or pedestal mount!
 

Bubbles Galore

Active member
Joined
Apr 11, 2008
Messages
2,115
Reaction score
0
Points
36
Location
Michigan
Thanks for all the info guys. I am doing a brick mount for a little added security. Is it necessary to put a footing in for the autocashier? If so, I'm not looking forward to digging that in zero degree weather this weekend...
 

MEP001

Well-known member
Joined
Aug 30, 2007
Messages
16,665
Reaction score
3,946
Points
113
Location
Texas
You'll want to secure it well so it can't be pulled of its mount by a truck with a chain and stolen. When I worked for a distributor I got a call from a customer that theirs had gotten pulled over. The guy that originally installed it put 400 pounds of concrete in the base, but he used 5/16" lag bolts to anchor it. They had no trouble getting it loose from the ground but couldn't lift it into the truck. Luckily there was no real damage to the unit - I had to replace the base because it was full of concrete, but I anchored it with 3/4" wedge anchors, with two more long ones in the center sticking up like rebar, then filled it with concrete again.
 

Bubbles Galore

Active member
Joined
Apr 11, 2008
Messages
2,115
Reaction score
0
Points
36
Location
Michigan
I'm sure I will have to reference local building codes, but do I have to dig a 42" footing for the auto cashier or can I just pour a 16" slab? Before anyone asks, I have to dig 16" for the conduit lines anyway, so I figured I would just make the slab an equal depth...thoughts?
 

dreese

dreese
Joined
Sep 1, 2007
Messages
60
Reaction score
2
Points
8
I'm sure I will have to reference local building codes, but do I have to dig a 42" footing for the auto cashier or can I just pour a 16" slab? Before anyone asks, I have to dig 16" for the conduit lines anyway, so I figured I would just make the slab an equal depth...thoughts?
I would dig 6" piers on the corners of the slab (rent a post hole digger) and pour the pad in one piece. We have used this method successfully without the need for a full footing. You are talking about a pretty good amount of weight to support without heave, especially if you pour the pad at 16".
 

Bubbles Galore

Active member
Joined
Apr 11, 2008
Messages
2,115
Reaction score
0
Points
36
Location
Michigan
I would dig 6" piers on the corners of the slab (rent a post hole digger) and pour the pad in one piece. We have used this method successfully without the need for a full footing. You are talking about a pretty good amount of weight to support without heave, especially if you pour the pad at 16".
So, you're saying to dig 42" down 6" wide at each of the 4 corners?
 

dreese

dreese
Joined
Sep 1, 2007
Messages
60
Reaction score
2
Points
8
So, you're saying to dig 42" down 6" wide at each of the 4 corners?
Yep - this acts to anchor the pad as it "floats" separately from the rest of your concrete. We also usually place a bollard to protect the brick mount - this depends on your specific layout. As always, be sure you are not in violation of any local codes if applicable.
 