100' Conveyor does not mean 100" feet of equipment.. In a cold Climate you may need to start 10 feet inside each
door. Also dirt conditions can dictate line speed. Had a location with 2 mitter wrap combos with lower details under.. Hung the initial pre soak and
soap off the forst unitfrom struts to eliminate first arch. Then Triple foam wax and mini mitter followed by Arch with Rinse, Drying Agent , Sealer Wax, and setting arch Flash dryer then some drip space and 3 Blower arches. I think it was 85' from first to last piece. 150+ cars was possible but the limiting factor was human & payment processing - not tunnel equipment.